Projects

Specialist Paving

Halifax Parish Church Yard Restoration – Phase 2
Calderdale MBC

Value: £74,000

Duration: 18 weeks

Construction of new link path and steps/ramp including the taking up and relaying of stone flags together with stone walling.

Rochdale Road Shops, Blackley
Rowlinson Constructions Limited

Value: £117,000

Duration: March - September 2008

Specialist paving to shop frontages including saxon block paving and surfacing of rear passageways.

Gorse Hill NRA, Final Phase
× Gorse Hill NRA, Final Phase

Gorse Hill NRA, Final Phase

Gorse Hill NRA, Final Phase
Trafford MBC

Value: £145,000

Duration: March - June 2008

Laying of saxon flags and block paviours. Installation of drainage channels and bitmac surfacing to rear passageways.

Castle Quay
Manchester Ship Canal Properties

Value: £2,000

Duration: February 2008

Lift and relay existing paving slabs.

Sir Matt Busby Way
Trafford MBC

Value: £36,000

Duration: December 2007

Renewal of flagged footway with paviours and blocks.

Altrincham Town Centre Refurbishment
× Altrincham Town Centre Refurbishment

Altrincham Town Centre Refurbishment

Altrincham Town Centre Refurbishment
Trafford MBC

Value: £1,000,000

Duration: April 2007 - March 2008

Specialist paving and block work associated with the refurbishment of Altrincham Town Centre including the construction of parking bays and pedestrian areas.

Halifax Parish Church Yard Restoration – Phase 1
× Halifax Parish Church Yard Restoration – Phase 1

Halifax Parish Church Yard Restoration – Phase 1

Halifax Parish Church Yard Restoration – Phase 1
Calderdale MBC

Value: £70,000

Duration: June – September 2006

Restoration of church yard including taking up and relaying of york stone flags and headstones and drainage works.