Gorse Hill Park Entrance
Trafford MBC
Value: £17,000
Duration: September 2008
Refurbishment of park entrance including tegular edging, drainage and surfacing.
Nansen Park
Trafford MBC
Value: £34,000
Duration: July 2008
Construction of children’s playground including construction of bases and installation of equipment.
Victoria Park Junior School
Trafford MBC
Value: £15,000
Duration: February - March 2008
Provision of additional car parking spaces within the curtilage of the school including kerbing, surfacing, installation of a cycle shelter and landscaping to surrounds
Parks Depot Improvements
Calderdale MBC
Value: £116,000
Duration: October 2006 – January 2007
Improvements to Council’s Park Depots including gates, fencing, additional storage bays, concrete slabs, drainage and demolition.